Fairfield, Ohio
| Fast Facts | |
| Scope | Safety study and mini roundabout design for an urban unsignalized intersection |
| Services | Safety study, topographic survey, easement and right-of-way plan preparation, utility relocation coordination, construction administration |
| Construction Cost | $763,421 |
| Client | City of Fairfield |
The Project:

The City of Fairfield partnered with Choice One Engineering to address a persistent safety problem at the stop-controlled intersection of Ross Road and Woodridge Boulevard. The primary goal was to better understand what was causing crashes and identify the right solution for the corridor and the community.
The Challenge:
The intersection sits in a compact urban setting with limited room for improvements. At the same time, crash history showed a need for a solution that would meaningfully improve safety without impacting nearby infrastructure or properties.
How We Helped:
Choice One Engineering conducted a safety study that evaluated crash history, traffic operations, and potential improvement alternatives. After comparing several options, a mini roundabout emerged as the best solution, improving both safety and traffic flow within the available space.
The Result:The City moved forward with the mini roundabout, with Choice One Engineering completing final design for the roundabout. The project delivers immediate safety improvements and a