Construction Sequence

Phase 1: this phase is to consist of the installation of all proposed waterline, sanitary sewer and storm sewer along CR-25A. The contractor shall also install the proposed sanitary and waterline along Leon Pratt Drive. No roadway work along CR-25A nor Leon Pratt Drive shall be completed as part of this phase. CR-25A must remain open to two-way traffic during this phase.

This phase shall be substantially completed by December 15, 2018.

Phase 2: this phase is to consist of the installation of all proposed pavement widening, shoulder embankment, pavement planing, resurfacing, pavement marking and signage along CR-25A only. CR-25A will be closed to thru traffic.

This phase shall not start work until after February 4, 2019 and must be completed before July 31, 2019. This phase is to be completed within a 45 calendar day period. See sheet 8 for road closure plan. Contractor cannot invoice for stored materials until after January 1, 2019.

Phase 3: this phase is to consist of the installation of all proposed pavement, curbing, storm sewer, pavement marking and signage for the new Leon Pratt Drive.

This phase shall not start work until after January 1, 2019 and must be completed before July 31, 2019. However the 45 day construction timeframe stated in phase 2 will not be subjected to this phase. Contractor cannot invoice for stored materials until after January 1, 2019.

Phase 4: this phase is to consist of the final seeding and mulching for the entire project. This phase shall be completed between September 15, 2019 and October 15, 2019.

Project Details

Project Description:

The construction of Leon Pratt Drive starting at the intersection of CR-25A and continuing to the east 3650′ in the City. The installation of asphalt pavement, curb and gutter, and storm sewer. Sanitary and waterline installation along CR-25A to the new roadway and then down Leon Pratt Drive. The work shall also consist of widening CR-25A to include a new southbound left turn lane onto Leon Pratt Drive.

 

Project Manager:

Mitchell J. Thobe

 

Project Funding:

ODOT Jobs & Commerce, ODSA, JobsOhio

 

Engineer’s Estimate:

$3,227,512.25

 

Bid Documents & Plans:

Available from Choice One Engineering Corporation by emailing Brittany Clinehens at bnc@choiceoneengineering.com.

 

Bid Documents & Plans Cost:

Electronic copies are available for no cost. Hard copies are available for an additional fee and are non-refundable; checks made payable to Choice One Engineering.

 

Bid Opening:

Thursday, May 24, 2018, 10:00 a.m. at the Council Chambers, 701 Parlette Court, Wapakoneta, Ohio 45895

Bid Form, Addenda, & Bid Tab

Bid Form:

Click here to download the quantities in Microsoft Excel for bid preparation use.

* Please note that formulas, etc., are the responsibility of the user and that the hard copy included with the bid packet is binding.

Addenda:

None at this time.

Bid Tab:

Will be available on or after May 24, 2018.

Bidders List

City of Wapakoneta
Chad Scott
419-738-3011
 
VTF Excavation, LLC
Aaron Bath
419-586-3077
 
The Builders Exchange
Kristin Niemeyer
937-278-5723 x201
 
Hohenbrink Excavating
Nick Hohenbrink
 
Tom’s Construction
Bret Liming
419-678-2457
 
Shinn Bros., Inc.
Bob Uhlenhake
419-586-5000
 
The Shelly Company
Jason Kreischer
 
Eagle Bridge Co.
Thomas J. Frantz
937-492-5654
 
Helms & Sons Excavating
Jeremy Nichols
419-422-7738
 
RB Jergens Contractors, Inc.
Andy Shaffer
937-669-9799
 
ConstructConnect
Mary “Joy” Sayre
323.602.5079 ext. 75323
 
Kinnison Excavation
Dave Kinnison
 
GovWin-Onvia
Jacqueline Sessa
(206) 373-9150
 
Construction Journal
Donna Dybzinski
(440) 826-4700 Phone x 722
 
Double Jay Construction
Lee Overturf
937-832-3123
 
Dodge Data & Anlaytics
800-393-6343
 
Brumbaugh Construction
Troy Myers
(937) 692-5107
 

Category:
Description

Leon Pratt Drive and CR-25A Improvements

City of Wapakoneta, Auglaize County

Bid Opening Date:
Thursday, May 24, 2018, 10:00 a.m.

Engineer’s Estimate:
$3,227,512.25

Substantial/Final Completion Dates

Construction Sequence

Phase 1: this phase is to consist of the installation of all proposed waterline, sanitary sewer and storm sewer along CR-25A. The contractor shall also install the proposed sanitary and waterline along Leon Pratt Drive.  No roadway work along CR-25A nor Leon Pratt Drive shall be completed as part of this phase. CR-25A must remain open to two-way traffic during this phase.

This phase shall be substantially completed by December 15, 2018.

Phase 2:  this phase is to consist of the installation of all proposed pavement widening, shoulder embankment, pavement planing, resurfacing, pavement marking and signage along CR-25A only. CR-25A will be closed to thru traffic.

This phase shall not start work until after February 4, 2019 and must be completed before July 31, 2019. This phase is to be completed within a 45 calendar day period. See sheet 8 for road closure plan. Contractor cannot invoice for stored materials until after January 1, 2019.

Phase 3:  this phase is to consist of the installation of all proposed pavement, curbing, storm sewer, pavement marking and signage for the new Leon Pratt Drive.

This phase shall not start work until after January 1, 2019 and must be completed before July 31, 2019. However the 45 day construction timeframe stated in phase 2 will not be subjected to this phase.  Contractor cannot invoice for stored materials until after January 1, 2019.

Phase 4:  this phase is to consist of the final seeding and mulching for the entire project.  This phase shall be completed between September 15, 2019 and October 15, 2019.

Project Details

Project Description:

The construction of Leon Pratt Drive starting at the intersection of CR-25A and continuing to the east 3650′ in the City. The installation of asphalt pavement, curb and gutter, and storm sewer. Sanitary and waterline installation along CR-25A to the new roadway and then down Leon Pratt Drive. The work shall also consist of widening CR-25A to include a new southbound left turn lane onto Leon Pratt Drive.

 

Project Manager:

Mitchell J. Thobe

 

Project Funding:

ODOT Jobs & Commerce, ODSA, JobsOhio

 

Engineer’s Estimate:

$3,227,512.25

 

Bid Documents & Plans:

Available from Choice One Engineering Corporation by emailing Brittany Clinehens at bnc@choiceoneengineering.com.

 

Bid Documents & Plans Cost:

Electronic copies are available for no cost. Hard copies are available for an additional fee and are non-refundable; checks made payable to Choice One Engineering.

 

Bid Opening:

Thursday, May 24, 2018, 10:00 a.m. at the Council Chambers, 701 Parlette Court, Wapakoneta, Ohio 45895

Bid Form, Addenda, & Bid Tab

Bid Form:

Click here to download the quantities in Microsoft Excel for bid preparation use.

* Please note that formulas, etc., are the responsibility of the user and that the hard copy included with the bid packet is binding.

Addenda:

None at this time.

Bid Tab:

Will be available on or after May 24, 2018.

Bidders List

City of Wapakoneta
Chad Scott
419-738-3011
 
VTF Excavation, LLC
Aaron Bath
419-586-3077
 
The Builders Exchange
Kristin Niemeyer
937-278-5723 x201
 
Hohenbrink Excavating
Nick Hohenbrink
 
Tom’s Construction
Bret Liming
419-678-2457
 
Shinn Bros., Inc.
Bob Uhlenhake
419-586-5000
 
The Shelly Company
Jason Kreischer
 
Eagle Bridge Co.
Thomas J. Frantz
937-492-5654
 
Helms & Sons Excavating
Jeremy Nichols
419-422-7738
 
RB Jergens Contractors, Inc.
Andy Shaffer
937-669-9799
 
ConstructConnect
Mary “Joy” Sayre
323.602.5079 ext. 75323
 
Kinnison Excavation
Dave Kinnison
 
GovWin-Onvia
Jacqueline Sessa
(206) 373-9150
 
Construction Journal
Donna Dybzinski
(440) 826-4700 Phone x 722
 
Double Jay Construction
Lee Overturf
937-832-3123
 
Dodge Data & Anlaytics
800-393-6343
 
Brumbaugh Construction
Troy Myers
(937) 692-5107